Abraham Lincoln Elementary School Annex
PROJECT DETAILS
Project: | Abraham Lincoln Elementary School Annex |
---|---|
Address: | 615 West Kemper Place |
Community: | Lincoln Park |
Ward: | 43 |
Description: | Proposed 3 story Annex to include 19 new classrooms, a new Dining Center, hybird cooking kitchen, roof top student area, selected renovations to the existing school, and associated site development work including a playground. Renovations scope is currently programmed to include a new elevator, ADA upgrades, and mechanical system upgrades.
Social Media
|
Contract Information: |
|
PROJECT PRESS RELEASES
PROJECT DOCUMENTS
- Exhaust Fan Installation and Temporary Closure of Kemper Place May 24, 2016
- Progress Update and Look-Ahead Schedule Weeks of August 24 & 31, 2015
- Progress Update and Look-Ahead Schedule Weeks of August 17 & 24, 2015
- Progress Update and Look-Ahead Schedule
Weeks of August 10 & 17, 2015 - Progress Update and Look-Ahead Schedule
Weeks of August 3 & 10, 2015 - Progress Update and Look-Ahead Schedule
Weeks of July 27 & August 3, 2015 - Progress Update and Look-Ahead Schedule
Weeks of July 20 & 27, 2015 - Progress Update and Look-Ahead Schedule
Weeks of July 13 & 20, 2015 - Progress Update and Look-Ahead Schedule
Weeks of July 6 & 13, 2015 - Progress Update and Look-Ahead Schedule
Weeks of June 29 & July 6, 2015 - Progress Update and Look-Ahead Schedule
Weeks of June 22 & 29, 2015 - Progress Update and Look-Ahead Schedule
Weeks of June 15 & 22, 2015 - Progress Update and Look-Ahead Schedule
Weeks of June 8 & 15, 2015 - Progress Update and Look-Ahead Schedule
Weeks of June 1 & 8, 2015 - Progress Update and Look-Ahead Schedule
Weeks of May 25 & June 1, 2015 - Lincoln Look Ahead Work Schedule Weeks of June 1 through July 31.
- Progress Update and Look-Ahead Schedule
Weeks of May 11 & 18, 2015 - Progress Update and Look-Ahead Schedule
Weeks of May 4 & 11, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Apr. 27 & May 4, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Apr. 20 & 27, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Apr. 13 & 20, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Apr. 6 & 13, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Mar. 30 & Apr. 6, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Mar. 23 & 30, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Mar. 16 & 23, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Mar. 9 & 16, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Mar. 2 & 9, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Feb. 23 & Mar. 2, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Feb. 16 & 23, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Feb. 9 & 16, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Feb. 2 & 9, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Jan 26 & Feb. 2, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Jan 19 & 26, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Jan 12 & 19, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Jan 5 & 12, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Dec 29, 2014 & Jan 5, 2015 - Progress Update and Look-Ahead Schedule
Weeks of Dec 22 & 29, 2014 - Progress Update and Look-Ahead Schedule
Weeks of Dec 15 & 22, 2014 - Progress Update and Look-Ahead Schedule
Weeks of Dec 8 & 15, 2014 - Progress Update and Look-Ahead Schedule
Weeks of Dec 1 & 8, 2014 - Progress Update and Look-Ahead Schedule
Weeks of Nov 24 & Dec 1, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Nov 17 & 24, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Nov 10 & 17, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Nov 3 & 10, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Oct. 27 & Nov 1, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Oct. 20 & 27, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Oct. 13 & 20, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Oct. 6 & 13, 2014 - Site Prep Weekly Update and Look-Ahead Schedule
Weeks of Sept. 29 and Oct. 6, 2014 - Community Intake Sessions
- Community Meeting Presentation (April 17, 2014)
- Community Meeting Presentation (July 25, 2014)
- Project Update Flyer
MORE PROJECT IMAGES
PROJECT MAP & STREET VIEW
Note: The street view image is an approximate location and view point. Use the arrows on the top left corner of the street view
() to rotate the image or use the arrows on the streets to move the view point.