ALL GENERAL CONTRACTS, SEPTEMBER 2017
Contractor: | F.H. Paschen, S.N. Nielsen & Associates, LLC |
Project: | Emiliano Zapata Academy Annex |
Address: | 2728 S. Kostner Avenue |
Amount of Contract: | $15,972,000.00 |
Contract Number: | C1580 |
Date: | 9/12/2017 |
Notes: | |
Contractor: | Friedler Construction Co. |
Project: | Ebinger Elementary School - Site Preparation Project |
Address: | 7350 West Pratt Avenue |
Amount of Contract: | $1,294,800.00 |
Contract Number: | C1585 |
Date: | 9/12/2017 |
Notes: | |
Contractor: | CCCJV |
Project: | Mt. Greenwood Elementary School Annex II - Site Preparation |
Address: | 10841 South Homan Avenue |
Amount of Contract: | $1,070,886.00 |
Contract Number: | C1584 |
Date: | 9/12/2017 |
Notes: | |
Contractor: | Path Construction Company, Inc |
Project: | Sheridan Elementary School Annex |
Address: | 533 West 27th Street |
Amount of Contract: | $6,371,000.00 |
Contract Number: | C1581 |
Date: | 9/12/2017 |
Notes: |